Cebu News

After four-day inspection, exec rules SM seaside Arena is safe

Mitchelle L. Palaubsanon - The Freeman

CEBU, Philippines — Following the four days of comprehensive inspections and clearing operations, SM Management has assured the public that the SM Seaside Cebu Arena remains intact and safe.

The assurance came during a briefing with Cebu City Mayor Nestor Archival and representatives of concerned government offices, safety consultants, and contractors on Saturday, November 21, after another round of inspection.

Arnel Gonzales, vice president of SM Mall of Asia Arena and SM Seaside Cebu Arena, said management took a cautious approach to ensure that the venue would be safe for spectators ahead of its scheduled major events, including Disney on Ice.

The measures were enforced after the second-day concert of American pop-rock duo LANY on November 12 was cancelled due to safety concerns involving the arena’s roofing or ceiling system.

Gonzales maintained that the incident involved residual construction materials and housekeeping-related debris rather than a failure of the ceiling structure.

“At the end of the day, we are always on the side of caution. What we did following the incident a few weeks ago was prioritize public safety,” Gonzales said.

He said management temporarily stepped back to ensure that the venue could provide the necessary safety assurances before proceeding with scheduled events.

“What we needed to address was basically housekeeping or cleaning. That was also what the AffixPro teams found during their inspection. Most of the materials were housekeeping-related debris that had not been immediately collected,” he said.

Four-day inspection

The inspection involved 36 personnel from SafeTech OSH Management Consultancy Service (AffixPro), representatives from the Office of the Building Official (OBO), Cebu City disaster management office, and Bureau of Fire Protection (BFP).

AffixPro owner Engr. Reny Almohlas said the team inspected the entire ceiling area and recovered residual construction materials and debris left above the ceiling during housekeeping.

He explained that these materials should have been collected during the contractor’s housekeeping operations but were missed during the initial clearing.

He added that the inspection confirmed that all ceiling components remained attached and secured, with no structural components found to have been loosened.

“Based on our inspection, all ceiling areas were inspected and cleared of debris. We are confident that the area is now free of debris and that no components of the ceiling structure have been loosened,” Almohlas said.

He added that the findings were reflected in the company’s final report, which indicated that the entire ceiling area had been inspected.

Certification and safety recommendations

In a Ceiling Inspection and Debris Recovery Clearance Certificate issued by SafeTech OSH Management Consultancy Service (AffixPro), the company certified that debris and unwanted materials found above the ceiling were already removed during the November 18 to 21 activities.

However, it clarified that the certification covered only areas that were accessible and visible during the inspection.

It also specified that the certificate should not be construed as a guarantee of the ceiling’s long-term condition, structural integrity, or safety, particularly in concealed areas that were not inspected.

Any new debris, damage, or unsafe condition arising after the inspection would also not be covered by the certification.

The company recommended regular preventive maintenance of the ceiling and its related components, as well as a comprehensive ceiling inspection at least once a year.

It also advised management to include above-ceiling areas in routine housekeeping and maintenance checks, particularly after construction, repair, or other activities that could leave materials or debris behind.

Any newly discovered debris, damage, or unsafe condition should be addressed immediately, the certification further stated.

Contractor admits housekeeping lapse

Meanwhile, Russel Sabanal, representing ceiling contractor Basic Machinery and Acoustics Corporation, acknowledged that they missed the materials during the housekeeping process and apologized for the incident.

Sabanal clarified that the loose item involved was not among the structural components installed as part of the arena’s ceiling system.

“We acknowledge that we were not able to completely clear the area during our housekeeping procedures. We apologize for that incident,” Sabanal said.

He explained that some materials may have been covered or overlooked during the initial clearing and inspection, resulting in their failure to detect and remove all the loose items.

City seeks written assurance

Archival, for his part, sought written assurances from the contractors and concerned agencies confirming that the ceiling had been inspected and cleared of debris and that no foreign objects remained that could potentially fall into the arena.

The safety consultant, ceiling contractor, and representatives of the concerned government offices signed the document during the briefing.

The mayor also requested copies of the video footage documenting the inspection and clearing operations to form part of the city’s official documentation.

Architect Emmanuel Cuizon, assistant head of the OBO, said the office had discussed the findings with the ceiling contractor and safety management consultant.

Harold Alcontin, representing the CCDRRMO, also acknowledged the inspection and clearing operations conducted by AffixPro and the third-party inspection team.

He said the video documentation helped establish that the inspection and clearing activities were undertaken despite the limited physical access to portions of the ceiling.

The BFP Special Rescue Force likewise attested to the thorough inspection conducted to ensure that the ceiling area had been properly checked.

Arena prepares for disney on ice

With the inspection completed, SM management said the arena was preparing to welcome spectators for its upcoming events, starting with Disney on Ice on November 28.

Gonzales said the show would mark the first staging of Disney on Ice in Cebu.

He expressed optimism that the event would attract more than 100,000 families and said management hoped to make it an annual Christmas tradition in the city.

Beyond entertainment, Gonzales said the arena was expected to contribute to Cebu’s tourism industry by attracting visitors from other parts of the Philippines and neighboring Southeast Asian countries.

The influx of event goers is also expected to benefit micro, small and medium enterprises, particularly businesses providing food, accommodation, transportation and other services.

Gonzales thanked the Cebu City Government, OBO, disaster management personnel, BFP and the company’s contractors for their cooperation during the inspection and preparations.

“We are working together to assure the public that this venue remains safe and meets world-class standards. We will be able to host the events scheduled to take place here in Cebu, starting with Disney on Ice next week,” he added. — (FREEMAN)

TRENDING

  • Latest
Latest
Latest
abtest
Recommended
Are you sure you want to log out?
X
Login

Philstar.com is one of the most vibrant, opinionated, discerning communities of readers on cyberspace. With your meaningful insights, help shape the stories that can shape the country. Sign up now!

Get Updated:

Signup for the News Round now

FORGOT PASSWORD?
SIGN IN
or sign in with