Involving capitol's previous administrations: ?143M disallowances

CEBU, Philippines — The Commission on Audit (COA) has flagged over ?143 million in disallowed transactions involving the Cebu Provincial Government, covering unresolved audit issues that span multiple administrations from as far back as 2007 up to 2024.
In a Statement of Audit Suspensions, Disallowances, and Charges (SASDC) dated July 3, 2025, COA-7 reported that ?143,373,175.32 worth of audit notices remain unsettled as of June 30, 2025.
Governor Pamela Baricuatro received the official copy of the report last Monday, July 14, which was also forwarded to provincial accountant Janet Guaren for appropriate action.
Of the total flagged amount, ?126,479,744.92 were long-standing disallowances, while ?1,016,185.46 came from beginning balances of unresolved issues in previous audits.
A negative adjustment of ?122,755.06 was recorded for the second quarter, effectively reducing the suspension balance to ?16,893,430.40.
In response, Baricuatro directed the Provincial Legal Office to initiate recovery actions against the individuals and entities named in the disallowances.
“The legal (team) is already working on it based sa among meeting,” said Baricuatro.
Provincial administrator Joseph Felix Mari "Ace" Durano said the flagged transactions involved government expenses made by the past administration.
“Kung kinsa ang nakadawat atong kwartaha, kinahanglan i-uli,” Durano said.
Many of the questioned transactions involved infrastructure projects and public works awarded between 2007 and 2015, according to the COA report.
Among the contractors cited were Supreme ABF Construction & Supply Co. Inc., WTG Construction & Development Corp., and Beecartine Construction & Supply, all of whom were awarded contracts that COA said lacked proper documentation or didn’t fully comply with procurement regulations.
The report also named several public officials involved in the projects, including former governor Hilario P. Davide III, who was held liable for ?122,755.06 in mobilization fees that weren’t recovered for the construction of the Bahay Pag-asa rehabilitation center in Naga City.
That amount, however, was eventually settled on March 21, 2024, and officially cleared by a Notice of Settlement from COA dated November 12, 2024.
Other officials involved in the same project were former provincial treasurer Roy Salubre, ex-provincial accountant Marieto Ypil, budget officer Danilo Rodas, provincial engineer Hector Jamora, and contractor Sydney Carcel of YES Construction.
The SASDC also cited former governor Gwendolyn F. Garcia, who was listed in several disallowance notices for various infrastructure projects implemented during her previous terms, specifically in the years 2008, 2012, and 2013.
In one entry, Garcia and several others were held liable for ?104,500.00 under Notice of Disallowance No. 2015-009, issued in relation to a 2012 project.
COA hasn’t yet disclosed which of the disallowed amounts are currently under appeal or litigation, leaving the total recoverable amount still unclear.
The audit report is part of COA’s quarterly issuance of SASDCs, which aim to ensure fiscal accountability among government agencies and promote the proper use of public funds.
Durano assured that following the governor's directive, the next step would be for the Provincial Legal Office to send notices to all recipients of the disallowed funds, instructing them to return the money.
"Our next step would be for legal to write all the recipients to return the money," Durano said. — (FREEMAN)