MGEN eyes Meralco baseload contract for Atimonan revival

From AB Capital's The Opening Bell: Three Moves
Event
MGEN plans to bid for Meralco's 900MW baseload supply contract under a 15-year power supply agreement (PSA), which could revive its long-delayed 1,200MW Atimonan coal-fired power plant in Quezon. The project has faced regulatory hurdles and changes in fuel technology over the past decade.
View
Securing a long-term PSA is critical to making Atimonan bankable by providing contracted demand to support project financing. We note, however, that the 900MW contract covers only part of the plant's capacity. Atimonan is not in our forecasts and would represent upside optionality for MGEN if it wins the contract and proceeds with development.
Catalyst
Expressions of interest are due this week, followed by a Nov. 6 pre-bid conference and Dec. 9 bid submission deadline. The key is whether MGEN can secure the contract on terms that support the project's economics.
Action
If MGEN wins the contract, we see this as another positive catalyst for MER following the regulatory rate reset. Atimonan would provide a long-term growth opportunity, although its financial contribution would only begin in 2031.
Disclaimer: The information, analyses, and views contained herein is based on sources which we, AB Capital Securities, believe are reliable, but is not guaranteed by us and is not to be considered all inclusive. It is not to be construed as an offer or solicitation of an offer to sell or buy the securities herein mentioned. AB Capital Securities and its Directors and Officers and/or members of their families may have a position in the securities herein mentioned and may make purchases and/or sales of the securities from time to time in the open-market and otherwise.