Balamban LGU questioned over flood control project

Jonnavie Villa - The Freeman

CEBU, Philippines — The Commission on Audit (COA) has recommended the municipality of Balamban to submit the updated and accurate revisions as to the progress of a flood control infrastructure project which has been found incomplete despite claims of full completion.

In its 2023 Annual Audit Report, COA found out that the Flood Control Structure along Cebu Industrial Park Developers, Inc. (CIPDI) in Barangay Arpili, Balamban, which had a contract cost of P9.7 million, was found to be only 87.73 percent completed instead of the 100 percent reported.

“The infrastructure project for the Construction of Flood Control Structure along Cebu Industrial Park Developers, Inc. (CIPDI), Arpili, Balamban, with a contract cost of ?9,762,772.32, was found to be only 87.73 percent completed, contrary to the reported 100 per cent accomplishments stated in the Statement of Work Accomplished, resulting in a deficiency of 12.27 percent or ?1,198,286.02,” reads a portion in the report.

The discrepancy of the project with its reported completion and actual progress was unveiled during an inspection by the Commission on Audit (COA) Technical Audit Group.

The audit team conducted an inspection on June 5, 2023 and revealed that the structure was still far from the 100 percent completion indicated in the Statement of Work Accomplished dated August 4, 2022.

Further, the audit team revealed that the reason for the shortcoming was because of the reduction in the length of the structure.

According to the original plans, the flood control project was intended to span a total of 420 meters. However, the inspection found the actual length to be only 393.5 meters, with 198 meters on the left side and 195.5 meters on the right side.

With this, the municipal engineer explained to the audit department that under-accomplishment was due to a deviation from the original plan.

According to him, the initial plan was to construct it around the back office of CIPDI, but this was not permitted.

“As a result, the flood control structure was constructed directly over a deeper section, compensating for the reduced length as a compromise,” reads the audit report.

The COA stated that if the deviation is not properly explained with enough evidence, the Municipality of Balamban could face a financial loss of P1,198,286.02.

Further, the audit team recommended that the Municipal Engineer submit updated documentation, including a revised plan and any variation orders related to the changes in the design.

“We recommended and Management agreed to substantiate their claims by having the Municipal Engineer submit the revised plan and variation order, if any, along with updated documentation regarding the change in design to accommodate actual field conditions and compensate for the reduction in the project’s length,” the report reads. — (FREEMAN)

COMMISSION ON AUDIT

  • Latest
Latest
Latest
abtest
Recommended
Are you sure you want to log out?
X
Login

Philstar.com is one of the most vibrant, opinionated, discerning communities of readers on cyberspace. With your meaningful insights, help shape the stories that can shape the country. Sign up now!

Get Updated:

Signup for the News Round now

FORGOT PASSWORD?
SIGN IN
or sign in with