Yearender: DOTC rocked by scandal of the year
The year 2007 could go down in the history of the Department of Transportation and Communications (DOTC) as the most unpleasant with the eruption of the national broadband network scandal.
The ruckus over the deal forged by DOTC Secretary Leandro Mendoza with the Chinese telecommunications firm ZTE Corp. for the latter to build a national broadband backbone spanning the whole length of the country had led to a political fallout between President Arroyo and one of her staunchest political allies, Speaker Jose de Venecia, Jr.
It even caused the resignation of Commission on Elections chairman Benjamin Abalos.
While
“Not really. We in the DOTC believe that we did no wrong on ZTE,”
“As a matter of fact, we did our homework. What happened was that there were many side issues that came into the picture. But whether it was necessary and whether the price was right, I think the Senate has not really determined if there was overpricing or not,”
“We submitted our due diligence, we did some comparison with suppliers from the
The former Philippine National Police (PNP) director general claimed that 2007 could even be a banner year if trust and credibility was to be made as yardstick for government departments.
“Well, if we’re going to look into that, then 2007 is a banner year for the DOTC. There are so many investors going to us. And these are investors with funds,”
“The credibility is there,”
STAR in the thick of it
The ZTE controversy erupted when Philippine Star columnist Jarius Bondoc, in his widely-read column Gotcha last June 22, exposed that the “supply contract” signed by Mendoza with ZTE president Yu Yong in Boao, China last April 21 was declared “stolen” by DOTC Assistant Secretary Lorenzo Formoso during a forum.
The contract signing, which was witnessed by no less than the President herself, was then already being criticized by business groups who questioned the necessity of the billion-peso project and the DOTC’s silence on the details of the agreement.
In a speech at the Ateneo Professional Schools-sponsored forum in
In a subsequent update on the contract papers, DOTC said the theft occurred at the hotel room of Emmanuel Nino Wee Ang, the
The DOTC later downplayed the theft of the case, saying they have reconstituted the contract.
The controversy raged further when Bondoc, in a subsequent column last August, named Abalos as the powerful government official who intensely lobbied for ZTE Corp. to bag the deal, claiming that the poll chairman had received bribes in cash and sexual favors to push for the Chinese group.
Bondoc’s series of articles on NBN contract irregularities led to a Senate investigation on the contract and the resignation of Abalos.
In the Senate hearings, the son and namesake of Speaker de Venecia, Jose “Joey” III, surfaced to testify about Abalos’ aggressive lobbying and the official’s efforts to dissuade him from pursuing the unsolicited offer of his company Amsterdam Holdings, Inc (AHI) to establish a broadband network for the country at no expense to the government under a build-operate-transfer scheme.
In the course of his Senate testimony, the younger de Venecia said the President’s husband had “advised” him to “back off” from the project in one of his meetings with Abalos at the Wack Wack Golf and Country Club in Mandaluyong.
Former NEDA chief Romulo Neri, for his part, also exploded a bombshell when he testified that Abalos offered him a bribe of P200 million to endorse the ZTE-NBN project.
“Nothing. It has been cancelled already,”
The DOTC’s recourse was to bid out the project to interested local telecommunications companies.
Missing NAIA III
Another red mark for the DOTC was its failure to open the controversial Ninoy Aquino International Airport (NAIA) Terminal III this year.
The collapse of a 100-square-meter portion of the ceiling at the arrival lobby came a few days before a scheduled soft opening of the facility by the Manila International Airport Authority (MIAA).
“We’re not talking of timetables here anymore,” he said.
The airport was originally scheduled to open last April but suffered delays in its completion.
The said airport, which straddles the towns of Sta. Barbara and Cabatuan, was built by two Japanese construction firms Taisei and Shimizu Joint Venture and was funded by a special yen loan package of the Japan Bank for International Cooperation (JBIC).
The airport, built on a 188-hectare area, was designed to meet the demand for a larger terminal brought about by the increasing number of passengers and cargo traffic in
The new airport reportedly boasts of state-of-the-art facilities, including landing and navigation systems, a modern terminal and control tower buildings, a runway 2.5 km long and 45 meters wide, a passenger terminal with 12,000 sq. m of space and a 1,281 sq. m-cargo terminal.
The
The airport is being constructed on a 182-hectare tract of land in
The new airport will provide a more effective and efficient air transportation system in the regional growth area of Negros Occidental.
From an initial project cost estimate of P4.24 billion, the project cost has swelled to around P6.2 billion.
Again like the new
“Insofar as project implementation is concerned, insofar as delivery of services is concerned, we don’t have any problem,”