MANILA, Philippines - Forty-one of the Metro Manila Development Authority’s (MMDA) flood control projects (FCPs) in 2012 failed to serve their purpose because of “inefficient implementation due to inadequate planning,†the Commission on Audit (COA) said in a report.
Of the 49 proposed FCPs with a P322-million budget in 2012, 41 or 83.5 percent of the projects – which cost P224 million – were completed only in the third and fourth quarters of the year and in January 2013 due to delays in the bidding process, according to the report, released early this week.
The COA report said the MMDA’s failure to start and finish its projects before it started raining in June “defeat(ed) the intent of mitigating or preventing the impact of the heavy rains to the public at large.â€
The eight remaining PCPs, worth P97.6 million, were not implemented at all during the same period.
The MMDA said several factors affected the schedule of the project implementation, among them the need to coordinate with various local officials and lawmakers.
State auditors, however, maintained that these problems could have been avoided had there been a project procurement management plan to support the annual procurement plan for the FCPs.